  • Road 423 project, Ness Ziona

    Road 423 project, Ness Ziona

    Road 423 project, Ness Ziona

    MAY 17, 2026

    Excited to share the beginning of construction works on the Road 423 project, Ness Ziona bypass to Rehovot.

    The project includes the construction of a new railway bridge above Margolin Street, which will be executed using the Top Down construction method.

    As part of the preparations for the bridge construction, the existing railway tracks shall be temporarily diverted.

    To enable this railway diversion, drainage channels and retaining walls are being constructed along the railway alignment throughout the project area.

    The contractor has commenced the construction of the drainage system and retaining walls.

    Kedmor Team: Raz Mor, Mor Machlev, Eilon Glazer, Rachel Davidson, Yelena Klainer, Alena Bichanov, Shoon Lae Kyaing

    Client – Netivei Israel
    Project Manager – IDEA ENGINEERING D.Y. LTD

    Road and Rail Designer – DEL Engineering LTD

    Soil consultant – Geosol Geotechnical Solutions

    Contractor– K.S.M.G. CONTRACTORS FOR INFRASTRUCTURE AND DEVELOPMENT WORKS LTD

    Photo Credit & QA – T.N.M. LIMITED Snir Aharon